Count It Yourself

City of Los Angeles · Since Approved by voters November 8, 2016

Proposition HHH supportive housing

Also called HHH bond

Uses City general obligation bond money to help pay for permanent supportive and affordable housing built by developers.

Quick answers 3

Proposition HHH is a $1.2 billion City bond for permanent supportive housing, approved by voters in November 2016 and repaid through property tax bills. The Housing Department lends the money to developers as gap funding, alongside tax credits and other sources. A unit in these reports means one apartment, usually a studio or one-bedroom; one apartment can house a person or a family. Most HHH money went to permanent supportive housing; a smaller share paid for shelters and service facilities, and some Project Homekey conversions, including $1.5 million for the former Ramada Inn in Venice and $1.3 million for Mollie Maison.

In the City homelessness budget, HHH had an adjusted budget of about $80.0 million in FY 2024-25. About $47.7 million was spent or encumbered and $32.3 million was carried into FY 2025-26, according to the CAO and Chief Legislative Analyst.

Permanent supportive apartments, including HHH projects, count toward the City's Alliance settlement target. As of September 30, 2025 the CAO counted 6,242 open permanent supportive apartments toward the settlement, with 2,356 more in progress.

Funding

Where the money comes from

Source of moneyAmountPeriod
Proposition HHH bond proceeds$80MFY 2024-25 adjusted budget, about $80.0 million Source

Cost and results

Money and results by year

Each year's money and results as the official reports state them. Tally LA doesn't divide one by the other: the counts are often running totals since the program began, or cover a different stretch of time than the spending.

FY 2021-22

Results reported

  • 1,142 apartments ready for people to move in, December 2021

Official cost figure

$596,486

average cost per apartment, 65 projects under construction as of December 2021 (City Controller)

The Controller hasn't published an average since 2022. The City's quarterly reports list each project's cost. As of Dec 31, 2024, 82 projects with 5,088 apartments were finished.

Sources: Proposition HHH Quarterly Report, July to December 2024 · The Problems and Progress of Prop. HHH (Feb 23, 2022)

FY 2020-21

Official cost figure

$531,000

average cost per apartment, projects under construction in 2020; $558,000 for projects still in planning (City Controller)

Only the cost figure was published for this year.

Source: Meeting the Moment: An Action Plan to Advance Prop. HHH

Accountability

Did it do what it said?

Three kinds of record, each with its sources. Tally LA doesn't grade programs.

What it set out to do

The ballot measure authorized $1.2 billion in bonds for supportive housing, affordable housing and facilities such as shelters, but did not set a number of apartments. The Housing Department's plan was 10,000 supportive apartments within 10 years of the 2016 vote: 7,000 paid for in part by HHH and 3,000 from other money, as cited by the City Controller in 2019 and 2022.

1 record

  1. Feb 23, 2022
    City Controller on the 10,000-apartment plan

    The Controller described the City's goal as 10,000 apartments in ten years.

    LA City Controller ↗ · Los Angeles City Controller ↗

What the government reports

As of December 31, 2025, the Housing Department and CAO reported 100 finished HHH-funded buildings with 6,374 apartments. HHH has committed money to 131 projects with 8,630 apartments, plus 24 facilities such as shelters; the other 2,256 apartments are in 31 projects not yet finished, some of which had not started construction. The counts include every apartment in each building: supportive apartments for people leaving homelessness, regular low-income apartments and manager apartments. In one group of buildings funded in 2017-18, for example, 417 of 615 apartments were supportive, 187 were low-income and 11 were for managers. Five bond sales through 2025 raised $1,113,985,000 of the $1.2 billion, and the program had spent $1,099,338,856 through December 31, 2025: $1,031,842,133 on housing loans and $67,496,723 on facilities. The last $86,015,000 in bonds (Series 2026-A) was sold in early 2026, completing the $1.2 billion. The CAO and CLA reported about $47.7 million in HHH spending or encumbrances in FY 2024-25, with $32.3 million carried forward.

Official results page ↗

3 records

  1. Apr 2, 2026
    Proposition HHH quarterly report, October to December 2025

    100 finished buildings with 6,374 apartments; 131 projects with 8,630 apartments have HHH funding, and 2,256 are in 31 unfinished projects. $1,099,338,856 spent through December 31, 2025.

    LA Housing Department and City Administrative Officer ↗
  2. Mar 25, 2026
    CAO and CLA homelessness spending report, FY 2024-25

    HHH: about $80.0 million adjusted, $47.7 million spent or encumbered, $32.3 million carried into FY 2025-26.

    City of Los Angeles, CAO and Chief Legislative Analyst ↗
Show 1 more
  1. Jan 8, 2026
    CAO Alliance progress as of September 30, 2025

    6,242 open permanent supportive apartments and 2,356 in progress counted toward the settlement.

    City of Los Angeles, Office of the City Administrative Officer ↗

What independent reviews found

The City Controller's February 23, 2022 report, "The Problems and Progress of Prop. HHH," found 8,091 apartments in 125 projects, of which 1,142 were ready for occupancy. Average cost per apartment was $520,879 for finished apartments, $596,486 for apartments under construction and $579,634 for apartments still in planning, with the highest at $836,895. Finished projects took an average of 3.4 years. The Controller said "the City has allocated just $58 million in HHH funds for interim housing and facilities," about 5 percent of designated funds, and that its earlier recommendations to change course on expensive or stalled projects had not been carried out. The Controller's October 8, 2019 review, "The High Cost of Homeless Housing," is the earlier report that cited the 10,000-apartment plan. No audit after 2022 was found as of October 2026.

1 record

  1. Feb 23, 2022
    City Controller: The Problems and Progress of Prop. HHH

    1,142 of 8,091 apartments in the pipeline were ready to live in. Average cost per apartment ranged from $520,879 (finished) to $596,486 (under construction); the highest was $836,895. Finished projects averaged 3.4 years.

    Los Angeles City Controller ↗

Not published. The FY 2026-27 HHH amount in the City homelessness budget was not found. The quarterly report counts apartments, not people: Tally LA has not found a published count of how many people have lived in HHH apartments or stayed housed. The report does not give one total split of supportive, low-income and manager apartments for all finished buildings. Cost per apartment for projects finished after 2022 was not found in one official place.

Promise tracker

Promised and reported

City of Los Angeles

Alliance settlement: shelter and housing spaces

70% of the promised figure
Promised
12,915
Actual
8,993

Required by June 13, 2027. Actual: Open as of Mar 31, 2026 (4,105 more in progress), per the CAO's May 2026 report.

More detail

Open and in-progress spaces add up to 13,098, which is 183 more than 12,915. The target was later amended to 14,000 by June 30, 2027, with at least 12,915 kept open through June 30, 2029. In its report on data through December 2025, the CAO said 357 units in four projects may not open by the deadline.

Program: Inside Safe, A Bridge Home and City interim housing, Tiny Home Villages, Project Homekey sites in the City, Proposition HHH supportive housing, Time-limited rental subsidies (rapid rehousing)

What does this mean?
The law behind it
  • LA Alliance for Human Rights v. City of Los Angeles (2022): A federal lawsuit settlement in which the City agreed to create 12,915 shelter or housing spaces by June 13, 2027. In 2025 Judge David O. Carter found the City had not met its obligations and appointed a monitor.
Sources (3)

City of Los Angeles

Proposition HHH supportive housing

Figures side by side
Promised
10,000
Actual
6,374

These two figures count different things, so Tally LA shows them side by side without a percent.

Supportive apartments planned within 10 years of the 2016 vote (7,000 from HHH, 3,000 from other money). Actual: Apartments open in HHH-funded buildings as of Dec 31, 2025.

More detail

8,630 apartments in 131 projects have HHH funding; 2,256 of them are in 31 projects not yet finished, some not yet under construction. The counts include every apartment in each building: supportive apartments, regular low-income apartments and manager apartments. The ballot measure did not specify a number of apartments. The 10,000 figure is the Housing Department's plan, cited by the City Controller in 2019.

Program: Proposition HHH supportive housing

What does this mean?
The law behind it
  • Proposition HHH (2016): A $1.2 billion City bond approved by voters in November 2016 to build supportive housing for people experiencing homelessness, plus affordable housing and facilities. Property owners repay the bonds through a charge on their property tax bills.

Sources: The High Cost of Homeless Housing: Review of Proposition HHH · Proposition HHH quarterly report, Oct 1 to Dec 31, 2025 (LAHD and CAO)

On Tally LA

Connected to this program

Common questions

Quick answers

How much money goes to Proposition HHH supportive housing?

Budget: $80M. FY 2024-25 adjusted HHH budget in the City homelessness budget, about $80.0 million (CAO and CLA, March 2026).

What was promised for Proposition HHH supportive housing?

10,000 supportive apartments in 10 years (Housing Department plan).

What results are reported for Proposition HHH supportive housing?

6,374 apartments finished in 100 buildings; 2,256 more in progress (Dec 2025).

Cite this page

Tally LA. "Proposition HHH supportive housing: Funding & Results." https://tallyla.com/programs/prop-hhh-supportive-housing/. Accessed November 20, 2026.